Below is an estimated timeline of the Garden St. Terraces project.
Timing |
Task |
Status |
Begin October 2005 |
Stakeholder & Public Outreach |
Ongoing |
March 2006 |
Parking negotiations with City of SLO |
Completed |
April 2006 |
City permit process and project review by City bodies including Architectural Review Commission, Planning Commission and City Council |
Completed Spring 2009 |
January 2010 |
Final Environmental Impact Report released to public |
Now Available |
January 27, 2010 |
Planning Commission -- Final EIR -- first review |
Scheduled Meeting Date |
February 24, 2010 |
Planning Commission -- Final EIR -- second review |
Scheduled Meeting Date |
Late March, 2010 |
Cultural Heritage Commission |
Anticipated Meeting Schedule |
April 2010 |
Architectural Review Commission |
Anticipated Meeting Schedule |
| June 2010 | City Council | Anticipated Meeting Schedule |
Ongoing - through Summer 2010 |
Preparation of construction drawings |
In progress |
Spring 2010 - Summer 2011 |
Project permits issued |
Anticipated |
Summer 2011 - Summer 2013 |
Construction |
Anticipated |