Project Timeline
Below is an estimated timeline of the Garden St. Terraces project.
Timing |
Task |
Status |
Begin October 2005 |
Stakeholder & Public Outreach |
Ongoing |
March 2006 |
Parking negotiations with City of SLO |
Completed |
April 2006 |
City permit process and project review by City bodies including Architectural Review Commission, Planning Commission and City Council |
Completed Spring 2009 |
January 2010 |
Final Environmental Impact Report released to public |
Now Available |
January 27, 2010 |
Planning Commission -- Final EIR -- first review |
Scheduled Meeting Date |
February 24, 2010 |
Planning Commission -- Final EIR -- second review |
Scheduled Meeting Date |
March 22, 2010 |
Cultural Heritage Commission |
Public Hearing |
April 19, 2010 |
Architectural Review Commission |
Public Hearing |
June 1, 2010 |
City Council |
Public Hearing |
February 11, 2011 |
Revised Project Submittal |
Completed |
July 25, 2011 |
Cultural Heritage Committee |
Scheduled Meeting Date |
August 15, 2011 |
Architectural Review Commission |
Scheduled Meeting Date |
October 4, 2011 |
City Council |
Scheduled Meeting Date |