Below is an estimated timeline of the Garden St. Terraces project.

     

Timing

Task

Status

Begin October 2005

Stakeholder & Public Outreach

Ongoing

March 2006

Parking negotiations with City of SLO

Completed

April 2006

City permit process and project review by City bodies including Architectural Review Commission, Planning Commission and City Council

Completed Spring 2009

January 2010

Final Environmental Impact Report released to public

Now Available

January 27, 2010

Planning Commission -- Final EIR -- first review

Scheduled Meeting Date

February 24, 2010

Planning Commission -- Final EIR -- second review

Scheduled Meeting Date

March 22, 2010

Cultural Heritage Commission

Public Hearing

April 19, 2010

Architectural Review Commission

Public Hearing

June 1, 2010

City Council

Public Hearing

February 11, 2011

Revised Project Submittal

Completed

July 25, 2011

Cultural Heritage Committee

Scheduled Meeting Date

August 15, 2011

Architectural Review Commission

Scheduled Meeting Date

October 4, 2011

City Council

Scheduled Meeting Date